Bill Barna of McSweeney Engineers addresses a large crowd that turned out to Waterfront Park Wednesday to hear about options for fixing Beaufort’s failing promenade. Wednesday’s meeting was the first time they were presented directly to the public. A big crowd — some 150 people — turned out to hear the details of three options that are on the table for preserving the promenade, a big part of the city’s coastal identity.

This option would better handle flooding and also be the most affordable, Barna said. The city is seeing tides at that elevation four to five times a year these days, Barna said. The top of the deck now is 6 feet, which is flood stage for king tides. The option isn’t considered viable because of the high cost, and it wouldn’t address the problem long-term. “Sea level is a thing, it is occurring, and it’s projected to keep going up,” Barna said. A recent city poll found that 56% of residents visit the park at least once a week.

While this option is likely to be “too far over the top” for most residents, the rendering is meant to foster discussion, said Bill Barna of McSweeney Engineers. Alternative 3, the seawall option, would involve replacing the platform and filling in the space underneath it with dirt. A rendering of Option 2 shows stairs and a berm that transitions the park to the new raised platform below the promenade. Unless residents say otherwise, Barna said, the rest of the 7-acre park could stay largely as it is under this option, Barna said. Just because the relieving platform is getting replaced doesn’t mean the overall park has to change much if residents like what they have, Barna said.

A third alternative adds a bunch of amenities like a dock extending into the water from the promenade and a splash pad, but that’s not expected to get a lot of positive feedback. It will take a couple of years to replace the relieving platform and the promenade including the permitting and funding part of the project, Barna said. The current relieving platform is 36 feet wide from the river extending toward the interior of the park.

It’s considered an unlikely alternative because of permitting challenges, which would drive up the costs. But it’s the most environmentally unfriendly option and therefore would be very expensive. Some may think that sounds like a “down and dirty” quick option, Barna said. The only change would be tying the existing park into the new promenade, whose elevation would be higher.

That option involves raising the platform underneath the promenade, which will raise the walkway. Duncan O’Quinn of O’Quinn Marine called the raised platform option “the way to go” because it’s the cheapest option and would be the quickest to build. It would be at least 2 feet higher than the current promenade, which would make its elevation 8 feet. It would, Barna said, amount to throwing “good money after bad.” Repairing and replacing the deteriorating piles would cost more than building a new relieving platform, he said. Barna, who first disclosed the scope of the problem to the city two years ago, unveiled renderings of five alternative solutions to committee members. “Flood conditions and deteriorating piles, that’s the need for this project,” Barna said.

Further along the coast, the stretch of beach and promenade between Adshade Road and Jackson information on this page Black will also welcome the public, with easy access to the sand provided via newly constructed beach access points. The project, in partnership with Eastern Solent Coastal Partnership (ESCP), involved construction of a new and improved seawall, beach replenishment, extensive timber groyne maintenance as well as an improved amenity area. The remaining construction works will then resume on 11 January and is planned to be completed in February 2027.

The promenade and part of the car park are expected to re-open at the earliest opportunity once the site has been cleared and is safe for public use. But the possibility, even if it is small, is why the city fenced off the promenade he said. “But every time I turn around things are more expensive.” Barna has said previously this isn’t much of an option because “it’s just going to get worse.” This option would require the removal of the concrete, dirt and decades of silt buildup. That open space can’t be seen now because of the fascia or skirt covering the front of the promenade.

During the meeting, Barna was asked if there was a danger of the promenade collapsing. Option 4 would include amenities like a splash pad, expanded shipping berths and a new dock that would extend farther into the river from the promenade. Alternative 3 involves building a large seawall and backfilling the areas underneath the platform where saltwater flows.